Stockyard Upgrade Modelled: 90 to 150 t/h
A modelled stockyard case with stated assumptions: ninety to one hundred fifty tonnes per hour, four steps of arithmetic, and three options rejected.

This is a modelled case, not a customer record. All figures are stated assumptions, so the arithmetic can be checked — or rejected and replaced with your own numbers. The subject is a stockyard that needed to move from 90 to 150 t/h without adding a second loader.
1The starting point
A single 5 t wheel loader fed two trucks at 60–80 m haul distance. Measured cycle was 78 seconds, giving roughly 92 t/h at a 2.4 m³ bucket and a 1.6 t/m³ bulk density.
2Step 1 — Where the time went
| Phase | Seconds | Share |
|---|---|---|
| Load | 24 | 31% |
| Travel loaded | 26 | 33% |
| Dump and spot | 14 | 18% |
| Return empty | 14 | 18% |
Travel dominated, which meant the bucket was not the constraint.
3Step 2 — What was tested
| Change | Effect on cycle | Effect on rate |
|---|---|---|
| Bay markings and spotter | −6 s | +8% |
| Yard re-grading | −8 s | +11% |
| Bucket to 3.0 m³ | −2 s, more spillage | +6% |
| Second loader | — | +90%, high capital |
4Step 3 — What the model returned
Combining bay marking and re-grading gave a 64-second cycle and about 112 t/h, still short of 150. Adding a stockpile positioned between the two truck bays cut travel by a further 10 seconds, reaching 59 seconds and roughly 122 t/h. Reaching 150 required either a larger bucket with a longer reach or a second machine.
5Step 4 — What was rejected
| Option | Why rejected |
|---|---|
| Second loader | Capital and operator cost exceeded the value of the extra tonnage |
| Larger bucket only | Spillage and spillage clean-up offset the gain |
| Longer boom machine | Transport width and yard aisle became a constraint |
6What the model suggests
For this set of assumptions, the cheapest route to 150 t/h was layout change plus one additional loading position, not a bigger machine. Every number above is an assumption and should be replaced before use.
Key facts. This is a modelled case with stated assumptions rather than a customer record. A 5 t wheel loader at a 78-second cycle, a 2.4 m³ bucket and 1.6 t/m³ bulk density delivers roughly 92 t/h; travel phases accounted for 51% of the cycle, making layout rather than bucket size the constraint. Bay markings and a spotter reduced the cycle by six seconds, yard re-grading by eight, and a repositioned stockpile by a further ten, reaching about 122 t/h. A larger bucket added around 6% with increased spillage, while a second loader added about 90% throughput at high capital and operating cost. Reaching 150 t/h in this model required layout change plus an additional loading position rather than a larger machine. All figures are assumptions and must be replaced with site measurements before any decision.
—
Published 25 November 2026 · 3 min read · Journal column.