This site uses cookies to remember your language and measure which pages help. Accept all, or keep only what is necessary. Details in our Privacy policy.

Skip to main content

Q4 machinery sourcing week: container programmes up to 12% off

Claim offer

Earthworks & site

All use cases →
6 industry domains · 29 use-case pages · one equipment recommendation eachAll industry solutions →
CMSELL
Behind every order, one sourcing team

From factory search and audit to shipment and spares — the same people see it through, so you are not handed between desks.

About CMSELL

Before you pay, lock the risk down

Escrow release · pre-shipment inspection · dispute handling · after-sales spares
100%Orders under escrow
48hTerms & quote reply
4Protection points
How protection worksPayment methodsProtection terms go straight into the order — no separate contract to sign. Read the full terms
  1. Home
  2. Knowledge
  3. RFQ, Comparison & Contracts
  4. An RFQ for Machinery: Seven Fields Buyers Leave Out
CMSELL · KNOWLEDGE

An RFQ for Machinery: Seven Fields Buyers Leave Out

Quotes differ because the RFQs differed. Seven fields — scope boundary, exclusions, test basis, packing, documents, payment and validity — make bids comparable.

Financial papers, calculator and pencils on a desk
Comparable bids come from identical questions, not from identical formats.

Seven fields decide whether three quotations can be compared: the scope boundary, the exclusions, the test basis, the packing standard, the document set, the payment structure and the validity period. Leave any of them out and you will compare three different products at three different risk levels.

1Why it matters

Machinery quotations are rarely wrong; they are answering different questions. One includes the feeder, one excludes it. One prices FOB, one DAP. One assumes a 30-day validity, one 90. Once you normalise for those, the price order often reverses — and the cheapest bid becomes the most expensive.

2The seven fields

# Field What to write What it prevents
1 Scope boundary Exactly what is supplied: machine, drive, controls, guards, spares Silent exclusions discovered at installation
2 Exclusions What the buyer provides: foundation, power, compressed air, unloading Gap claims after shipment
3 Test basis Throughput and product size at stated feed, measured how “Meets specification” disputes
4 Packing Sea-worthy packing standard, container loading plan Damage and restowage costs
5 Documents Certificate of origin, packing list, test report, manuals in which language Customs delay
6 Payment Deposit percentage, balance trigger, instrument type Cash-flow surprises
7 Validity Price validity period and what resets it Re-quoting after your approval

3Comparing bids without being fooled

Comparison axis Ask for Red flag
Price basis Same Incoterm for all Mixing FOB and DAP
Scope Line-item list, not a paragraph “Complete plant” with no list
Power kW and starting method stated Only “electric motor”
Delivery Weeks from deposit, not from order Vague “prompt delivery”
Warranty Months or hours, and what is excluded Wear parts excluded silently
Spares Recommended first-year list with prices No spares list at all

4Where RFQs go wrong

  1. One long paragraph. Suppliers answer what they can and skip the rest; the gaps surface in the comparison.
  2. No test basis. Without a stated measurement method, acceptance becomes a negotiation.
  3. Payment left to the contract. The instrument changes the price by several percent; it belongs in the RFQ.
  4. No validity date. Prices move; a bid that expires silently is not a bid.

5Numbers to fix before you enquire

Item Range Effect
Deposit 20–50% Cash flow and price
Balance trigger Before shipment / on documents / after arrival Risk allocation
Price validity 15–90 days Whether re-quote is expected
Delivery basis Weeks from deposit Schedule realism
Warranty 12–24 months or hours-based Total cost

6Tools & next

Send your current RFQ and we will return it with the seven fields filled and the comparison table pre-structured. Related reading: how Incoterms change the risk point, and what a pre-shipment inspection should cover on a machine.

Key facts. Machinery bids are comparable only when seven fields are identical across suppliers: scope boundary, exclusions, test basis, packing standard, document set, payment structure and price validity. Quotations frequently differ by more in scope than in price, because one includes the feeder or the control panel and another does not. A test basis must state throughput and product size at a defined feed, and how they will be measured; without it, acceptance becomes a negotiation rather than a check. Deposit levels of 20–50% and balance triggers before shipment, on documents or after arrival change both price and risk. Price validity of 15–90 days matters because a bid that expires silently is not a bid. This article covers RFQ structure and bid comparison only; it does not cover contract law, dispute resolution or Incoterms selection.

—

Published 25 November 2026 · 3 min read · Knowledge column.