This site uses cookies to remember your language and measure which pages help. Accept all, or keep only what is necessary. Details in our Privacy policy.

Skip to main content

Q4 machinery sourcing week: container programmes up to 12% off

Claim offer

Earthworks & site

All use cases →
6 industry domains · 29 use-case pages · one equipment recommendation eachAll industry solutions →
CMSELL
Behind every order, one sourcing team

From factory search and audit to shipment and spares — the same people see it through, so you are not handed between desks.

About CMSELL

Before you pay, lock the risk down

Escrow release · pre-shipment inspection · dispute handling · after-sales spares
100%Orders under escrow
48hTerms & quote reply
4Protection points
How protection worksPayment methodsProtection terms go straight into the order — no separate contract to sign. Read the full terms
  1. Home
  2. Insights
  3. Case Studies
  4. Stockyard Upgrade Modelled: 90 to 150 t/h
CMSELL · JOURNAL

Stockyard Upgrade Modelled: 90 to 150 t/h

A modelled stockyard case with stated assumptions: ninety to one hundred fifty tonnes per hour, four steps of arithmetic, and three options rejected.

Warehouse loading bays with a forklift and stacked pallets
A modelled case: the assumptions are stated so the arithmetic can be checked or rejected.

This is a modelled case, not a customer record. All figures are stated assumptions, so the arithmetic can be checked — or rejected and replaced with your own numbers. The subject is a stockyard that needed to move from 90 to 150 t/h without adding a second loader.

1The starting point

A single 5 t wheel loader fed two trucks at 60–80 m haul distance. Measured cycle was 78 seconds, giving roughly 92 t/h at a 2.4 m³ bucket and a 1.6 t/m³ bulk density.

2Step 1 — Where the time went

Phase Seconds Share
Load 24 31%
Travel loaded 26 33%
Dump and spot 14 18%
Return empty 14 18%

Travel dominated, which meant the bucket was not the constraint.

3Step 2 — What was tested

Change Effect on cycle Effect on rate
Bay markings and spotter −6 s +8%
Yard re-grading −8 s +11%
Bucket to 3.0 m³ −2 s, more spillage +6%
Second loader — +90%, high capital

4Step 3 — What the model returned

Combining bay marking and re-grading gave a 64-second cycle and about 112 t/h, still short of 150. Adding a stockpile positioned between the two truck bays cut travel by a further 10 seconds, reaching 59 seconds and roughly 122 t/h. Reaching 150 required either a larger bucket with a longer reach or a second machine.

5Step 4 — What was rejected

Option Why rejected
Second loader Capital and operator cost exceeded the value of the extra tonnage
Larger bucket only Spillage and spillage clean-up offset the gain
Longer boom machine Transport width and yard aisle became a constraint

6What the model suggests

For this set of assumptions, the cheapest route to 150 t/h was layout change plus one additional loading position, not a bigger machine. Every number above is an assumption and should be replaced before use.

Key facts. This is a modelled case with stated assumptions rather than a customer record. A 5 t wheel loader at a 78-second cycle, a 2.4 m³ bucket and 1.6 t/m³ bulk density delivers roughly 92 t/h; travel phases accounted for 51% of the cycle, making layout rather than bucket size the constraint. Bay markings and a spotter reduced the cycle by six seconds, yard re-grading by eight, and a repositioned stockpile by a further ten, reaching about 122 t/h. A larger bucket added around 6% with increased spillage, while a second loader added about 90% throughput at high capital and operating cost. Reaching 150 t/h in this model required layout change plus an additional loading position rather than a larger machine. All figures are assumptions and must be replaced with site measurements before any decision.

—