Warranty covers the part; spares cover the downtime. Two clauses decide whether a failure costs a day or a month, and both are negotiable at order.

Warranty and spares answer different questions. Warranty says who pays for a failed part. The spares clause says how long the machine stands still. A contract with the first and not the second covers the cheapest part of a breakdown.
1Why it matters
Downtime cost usually exceeds part cost by an order of magnitude. Yet most orders negotiate warranty length for hours and never discuss parts availability, lead time or where spares are held.
2Two clauses, four terms
| Clause | Term to negotiate |
|---|---|
| Warranty | Duration, hours limit, what is excluded |
| Warranty | Who pays freight on a claim |
| Spares | Availability period after delivery, typically 10 years |
| Spares | Maximum lead time for critical parts |
3Terms worth arguing about
| Term | Weak | Strong |
|---|---|---|
| Duration | 12 months | 12 months or 2,000 h, whichever first |
| Freight on claim | Buyer pays | Seller pays if defect confirmed |
| Parts availability | “As long as available” | 10 years from delivery |
| Critical part lead time | Not stated | ≤ 2 weeks, or stock held |
4Where warranty terms go wrong
- Duration without an hours limit. A machine running 20 h/day consumes warranty in months.
- Freight excluded. A covered part that costs a container to return is not covered.
- Wear parts silently excluded. Confirm the list, not the principle.
- No spares availability term. Support ends when the model does.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Warranty | 12–24 months or 2,000–6,000 h | Coverage |
| Parts availability | 8–15 years | Support life |
| Critical lead time | 1–6 weeks | Downtime |
| Freight on claim | Per contract | Claim value |
6Tools & next
Send your warranty section and we will return the four terms to add. Related reading: after-sales arrangements, and how to file a claim that holds.
Key facts. Warranty and spares answer different questions: warranty covers who pays for a failed part, while the spares clause covers how long the machine stands still, and downtime usually costs an order of magnitude more than the part. Four terms are worth negotiating: warranty duration with an hours limit, typically 12–24 months or 2,000–6,000 hours whichever comes first; who pays freight on a confirmed claim; parts availability after delivery, commonly ten years; and a maximum lead time for critical parts, ideally two weeks or stock held locally. A machine running 20 hours a day consumes a calendar-based warranty in months. Wear parts are often excluded and the exclusion list should be read rather than assumed. Support effectively ends when the model does, so availability should be a written term. This article covers warranty and spares terms only; it does not cover legal remedies or insurance.
—
Published 25 November 2026 · 3 min read · Knowledge column.
On this page
Need this checked against your site?
Send the working condition, the quantity and the destination port. The desk answers with a written specification and a traceable price — not a brochure.