- Writing an RFQ a Factory Can Actually Quote
Writing an RFQ a Factory Can Actually Quote
An RFQ fails when the supplier has to guess. Six blocks — duty, envelope, power, standard, delivery and commercial terms — make bids comparable.

A supplier who has to guess quotes the safest option, usually the largest machine. Six blocks remove the guessing: duty, envelope, power, applicable standard, delivery expectation and commercial terms.
1Why it matters
RFQ quality determines bid comparability. When three suppliers answer three different questions, price comparison is meaningless — one includes a feeder, one excludes installation, one assumes a different voltage. Normalising after the fact costs more time than writing the six blocks once.
2The six blocks
| Block | What to state | Why it matters |
|---|---|---|
| Duty | Throughput, product, hours per day, material | Sizes the machine |
| Envelope | Site access, foundation, ambient, altitude | Rules out unsuitable units |
| Power | Voltage, frequency, phase, starting limit | Determines motor and starter |
| Standard | Certification, test basis, acceptance criteria | Makes acceptance objective |
| Delivery | Required on-site date, shipping terms | Sets production slot |
| Commercial | Payment structure, validity, warranty, spares | Makes totals comparable |
3Wording that removes ambiguity
| Weak | Strong |
|---|---|
| “High capacity” | “120 t/h of granite, 0–500 mm feed, 0/20 and 20/40 mm product” |
| “Suitable power” | “380 V, 50 Hz, three-phase, star-delta starting only” |
| “Good quality” | “CE marking with declaration, ISO 9001 certificate, test report per lot” |
| “Soon” | “On site by 15 March, DAP to named address” |
4Where RFQs go wrong
- One paragraph of prose. Suppliers answer the parts they can and leave the rest blank.
- No test basis. Acceptance becomes a negotiation instead of a check.
- Commercial terms in a separate email. They change the price and must be in the same document.
- No validity date. Prices move; an expired bid is not a bid.
- No exclusion list. What the buyer supplies must be as explicit as what the seller does.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Machines per RFQ | 1–5 | Supplier attention |
| Required date | 4–24 weeks out | Feasibility |
| Bid validity | 15–90 days | Price certainty |
| Payment structure | Deposit / balance split | Price and risk |
6Tools & next
Send your last RFQ and we will return it restructured into the six blocks. Related reading: the seven fields buyers leave out, and how to compare quotations line by line.
Key facts. An effective RFQ removes the need for a supplier to guess, and guessing produces the largest, safest and most expensive option. Six blocks make bids comparable: duty with throughput, product and hours; envelope including access, foundation, ambient and altitude; power with voltage, frequency, phase and starting limit; the applicable standard and test basis; delivery expectation with shipping terms; and commercial terms covering payment, validity, warranty and spares. Weak wording such as “suitable power” should be replaced with a specific voltage and starting constraint, and “good quality” with named certification and a test basis. Commercial terms sent in a separate message change the price and must sit in the same document. A bid without a validity date is not a bid. This article covers RFQ structure only; it does not cover negotiation tactics, contract law or supplier selection scoring.
—
Published 25 November 2026 · 3 min read · Knowledge column.