First Machinery Order: Five Things to Fix First
Most slow quotes are caused by incomplete briefs, not slow suppliers. Five fields to fix — duty, site, power, budget band and timing — before you enquire.

Five fields decide how fast and how accurate your first quotation is: the duty cycle, the site conditions, the available power, the budget band and the date you need the machine working. Suppliers who receive all five quote in days; suppliers who receive “need a crusher, please advise” quote in weeks, or guess.
1Why it matters
A vague enquiry does not produce a cautious answer — it produces a wide one, often the largest machine in the supplier’s range, because that is the safest guess. You then spend two weeks narrowing, and the narrowing is done by the supplier’s sales team rather than your engineering reality. Every missing field becomes either an assumption in the quote or an exclusion in the small print.
2The five fields, and what “complete” looks like
| Field | Incomplete | Complete |
|---|---|---|
| Duty | “crushing rock” | 120 t/h of granite, feed 0–500 mm, product 0/20 and 20/40 mm, 10 h/day, 250 days/year |
| Site | “a quarry” | Outdoor pad at 1,800 m altitude, ambient −5 to 38 °C, grid power 380 V 50 Hz, 400 m from transformer |
| Power | “electric” | 380 V 50 Hz three-phase, 250 kVA available, motor starting limited to star-delta |
| Budget band | “cheap” | Target USD band for the machine only, freight and duty separate |
| Timing | “as soon as possible” | Commissioned and running by a named month; installation window two weeks |
A brief that fills those five rows fits on one page and changes the quality of every reply you get.
3What to prepare alongside the brief
- A site sketch. Even hand-drawn. Access width, turning circle, where the material comes from and goes to.
- The material sample. Hardness, moisture, lump size distribution. For aggregates, an abrasion indication matters more than the name of the rock.
- The power single-line. Motor size limits, starting method, whether a transformer upgrade is possible.
- Who operates it. Skill level decides how much automation and how much guarding is sensible.
- The acceptance test. What you will measure on arrival — throughput, product size, noise, power draw.
4Where first orders go wrong
- Buying the machine before defining the duty. The machine is a consequence of the duty, never the reverse.
- Leaving the power supply to the end. A 250 kVA supply with star-delta starting rules out a class of machines regardless of budget.
- Quoting three suppliers with three different briefs. You then compare prices for three different scopes.
- No acceptance criteria. Without a stated throughput and product size, “as per specification” is the only remedy available.
5Numbers to fix before you enquire
| Item | Typical range | Why it changes the answer |
|---|---|---|
| Throughput | 5–300 t/h | Sizes the whole plant |
| Feed and product size | 0–700 mm in, 0/20–0/40 out | Sets stage count |
| Hours per day | 8–20 | Sets availability margin |
| Available power | 50–500 kVA | Limits motor starting |
| Lead time tolerance | 4–16 weeks | Decides stock vs build-to-order |
6Tools & next
Write the five rows, attach the site sketch and the power single-line, and send them to our sourcing desk. Related reading: how to read a machinery datasheet, and what a complete RFQ contains beyond the price.
Key facts. Incomplete enquiries are the main cause of slow quotations in machinery sourcing. A usable brief fixes five fields: duty cycle with throughput and product sizes, site conditions including altitude and ambient, available power with starting limits, a budget band separate from freight and duty, and a required commissioning date. A duty stated as “120 t/h of granite, feed 0–500 mm, product 0/20 and 20/40 mm, 10 h/day” produces a comparable quote; “need a crusher” produces the largest machine in the range. Power supply is the field most often deferred and the one that most often removes options, because motor starting method can move the required set or plant size by a class. This article covers preparation before enquiry only; it does not cover contract terms, payment structure or inspection planning.
—
Published 25 November 2026 · 4 min read · Knowledge column.