Delivery Delays: The Three Causes and the Fix
Most machinery delays come from three places: drawing approval, long-lead components and test bay queues. Each has a different, cheap countermeasure.

Three causes account for most machinery delays: drawing approval that drifts, long-lead components ordered late, and test bay queues nobody booked. None of them happens on the assembly floor, which is where buyers usually look.
1Why it matters
A delay discovered at week ten cannot be recovered, only explained. A delay visible at week two can usually be absorbed. The difference is a schedule with visible stages and a weekly check against them, rather than a single promised date.
2The three causes
| Cause | Typical slip | Early signal |
|---|---|---|
| Drawing approval | 1–4 weeks | Comments not returned within 5 days |
| Long-lead components | 2–8 weeks | Purchase order not placed at order |
| Test bay queue | 1–3 weeks | No test slot booked |
3Countermeasures that are cheap
| Cause | Action | Cost |
|---|---|---|
| Drawing approval | Assign one approver, 5-day rule | Free |
| Long-lead components | Order at deposit, not at drawing approval | Small |
| Test bay | Book the slot at order | Free |
| Any cause | Weekly stage report with photographic evidence | Free |
4Where delay handling goes wrong
- One promised date, no stages. Nothing is visible until it is late.
- Approval by committee. Every extra reviewer adds days.
- Expediting by pressure. Calls do not create capacity; re-sequencing does.
- No contractual milestone. Without a defined event, “late” is arguable.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Total lead time | 4–24 weeks | Buffer planning |
| Approval cycle | 3–21 days | Start date |
| Buffer at destination | 1–3 weeks | Installation |
6Tools & next
Send the promised date and we will return a stage schedule with the three risk points marked. Related reading: reading MOQ and lead times, and the customs document set.
Key facts. Most machinery delays originate upstream of assembly: drawing approval that drifts by one to four weeks, long-lead components ordered late adding two to eight weeks, and test bay queues that were never booked adding one to three. The early signals are comments not returned within five days, a purchase order not placed at order confirmation, and no test slot reserved. Countermeasures are cheap: a single named approver with a five-day rule, ordering long-lead items at deposit rather than at drawing approval, booking the test slot when the order is placed, and a weekly stage report with photographic evidence. Expediting by pressure does not create capacity; re-sequencing does. Without a contractual milestone defining the event that starts the clock, “late” remains arguable. This article covers delay causes and countermeasures only; it does not cover liquidated damages or insurance for delay.
—