This site uses cookies to remember your language and measure which pages help. Accept all, or keep only what is necessary. Details in our Privacy policy.

Skip to main content

Q4 machinery sourcing week: container programmes up to 12% off

Claim offer

Earthworks & site

All use cases →
6 industry domains · 29 use-case pages · one equipment recommendation eachAll industry solutions →
CMSELL
Behind every order, one sourcing team

From factory search and audit to shipment and spares — the same people see it through, so you are not handed between desks.

About CMSELL

Before you pay, lock the risk down

Escrow release · pre-shipment inspection · dispute handling · after-sales spares
100%Orders under escrow
48hTerms & quote reply
4Protection points
How protection worksPayment methodsProtection terms go straight into the order — no separate contract to sign. Read the full terms
  1. Home
  2. Knowledge
  3. Delivery Delays & Exception Handling
  4. Delivery Delays: The Three Causes and the Fix
CMSELL · KNOWLEDGE

Delivery Delays: The Three Causes and the Fix

Most machinery delays come from three places: drawing approval, long-lead components and test bay queues. Each has a different, cheap countermeasure.

Worker moving palletised freight with a pallet jack
Delays rarely come from the workshop floor; they come from approvals and queues upstream.

Three causes account for most machinery delays: drawing approval that drifts, long-lead components ordered late, and test bay queues nobody booked. None of them happens on the assembly floor, which is where buyers usually look.

1Why it matters

A delay discovered at week ten cannot be recovered, only explained. A delay visible at week two can usually be absorbed. The difference is a schedule with visible stages and a weekly check against them, rather than a single promised date.

2The three causes

Cause Typical slip Early signal
Drawing approval 1–4 weeks Comments not returned within 5 days
Long-lead components 2–8 weeks Purchase order not placed at order
Test bay queue 1–3 weeks No test slot booked

3Countermeasures that are cheap

Cause Action Cost
Drawing approval Assign one approver, 5-day rule Free
Long-lead components Order at deposit, not at drawing approval Small
Test bay Book the slot at order Free
Any cause Weekly stage report with photographic evidence Free

4Where delay handling goes wrong

  1. One promised date, no stages. Nothing is visible until it is late.
  2. Approval by committee. Every extra reviewer adds days.
  3. Expediting by pressure. Calls do not create capacity; re-sequencing does.
  4. No contractual milestone. Without a defined event, “late” is arguable.

5Numbers to fix before you enquire

Item Range Effect
Total lead time 4–24 weeks Buffer planning
Approval cycle 3–21 days Start date
Buffer at destination 1–3 weeks Installation

6Tools & next

Send the promised date and we will return a stage schedule with the three risk points marked. Related reading: reading MOQ and lead times, and the customs document set.

Key facts. Most machinery delays originate upstream of assembly: drawing approval that drifts by one to four weeks, long-lead components ordered late adding two to eight weeks, and test bay queues that were never booked adding one to three. The early signals are comments not returned within five days, a purchase order not placed at order confirmation, and no test slot reserved. Countermeasures are cheap: a single named approver with a five-day rule, ordering long-lead items at deposit rather than at drawing approval, booking the test slot when the order is placed, and a weekly stage report with photographic evidence. Expediting by pressure does not create capacity; re-sequencing does. Without a contractual milestone defining the event that starts the clock, “late” remains arguable. This article covers delay causes and countermeasures only; it does not cover liquidated damages or insurance for delay.

—

Published 25 November 2026 · 3 min read · Knowledge column.