Currency Risk in a Machine Order: Three Levers
Between quotation and payment, a currency can move more than the machine's margin. Three levers — currency, timing and clause — reduce that exposure.

A machinery order spans months between quotation and final payment. In that window a currency pair can move 5–10%, which for a machine with a 15% margin is most of the profit. Three levers reduce the exposure: which currency you contract in, when you fix the rate, and what the contract says if the rate moves.
1Why it matters
Buyers usually discover currency risk when the deposit is due, not when the order is placed. The exposure is created by the quotation, and it is either transferred, shared or accepted — but never eliminated.
2The three levers
| Lever | Option | Effect |
|---|---|---|
| Currency | Quote and pay in your own | Risk moves to seller, price rises |
| Currency | Quote and pay in seller’s | You carry the risk, price falls |
| Timing | Fix rate at order | Certainty, no upside |
| Timing | Fix at payment | Exposure, possible gain |
| Clause | Sharing band ±3–5% | Shared risk beyond band |
3Practical combinations
| Situation | Sensible approach |
|---|---|
| Small order, short lead time | Accept the exposure |
| Large order, long lead time | Forward contract or currency clause |
| Volatile currency pair | Currency clause with a band |
| Repeat buyer | Invoice in one currency consistently |
4Where currency handling goes wrong
- Quotation currency different from payment currency. An unhedged position nobody owns.
- Forward contract covering the wrong date. Payment dates move; hedges must follow.
- Sharing clause without a reference rate. “Official rate” is ambiguous.
- Ignoring the deposit timing. The deposit is exposed from order, not from shipment.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Order value | — | Exposure size |
| Lead time | 4–24 weeks | Exposure duration |
| Pair volatility | 3–15% per year | Risk |
| Hedge cost | 0.2–1.5% | Overhead |
6Tools & next
Send the currency pair and payment schedule and we will show the exposure by milestone. Related reading: payment instruments compared, and milestone structure.
Key facts. Currency exposure in machinery orders is created at quotation and lasts until final payment, often several months, during which major pairs can move 5–10% against a machine margin of around 15%. Three levers manage it: the currency of quotation and payment, which transfers or accepts the risk; the timing of rate fixing, either at order for certainty or at payment for exposure; and a contract clause sharing movement beyond a band of about ±3–5%. A quotation in one currency with payment in another is an unhedged position that usually belongs to nobody. Forward contracts must match actual payment dates, which frequently shift. A sharing clause needs a named reference rate to be workable. The deposit is exposed from order confirmation rather than from shipment. This article covers currency risk management only; it does not cover treasury policy, accounting treatment or speculative positions.
—