- Arrival Inspection: The 7 Days That Set Warranty
Arrival Inspection: The 7 Days That Set Warranty
Warranty claims weaken after the first week on site. Five checks in the first seven days preserve the evidence that decides claim or argument.

A machine’s warranty is only as strong as the evidence collected in its first week on site. Five checks — packaging, condition, completeness, documentation and trial run — decide whether a later defect is a claim or an argument.
1Why it matters
Damage in transit and defects from manufacture look identical three months later. If the crate was opened without photographs and the machine ran for a week before the first complaint, the supplier can reasonably argue the damage happened on site. Notification windows in most contracts are short, and they start at delivery, not at commissioning.
2The five checks
| Check | What to record | When |
|---|---|---|
| Packaging | Crate condition, marks, seal numbers | Before opening |
| Condition | Photographs of every face, close-ups of damage | At unpacking |
| Completeness | Packing list compared line by line | At unpacking |
| Documentation | Manuals, certificates, test reports, wiring diagrams | Before assembly |
| Trial run | No-load then load, parameters recorded | Before handover |
3Notification discipline
| Situation | Action | Deadline |
|---|---|---|
| Visible transit damage | Photograph, notify carrier and supplier | Same day |
| Missing items | Written notice against the packing list | 3 days |
| Functional defect | Written notice with measurements | 7 days |
| Hidden defect | Written notice with evidence | Per contract |
4Where arrival inspections go wrong
- Opening crates before photographing them. The only evidence of transit damage is lost.
- Signing the delivery note clean. Signature without inspection weakens every later claim.
- No trial-run record. Without parameters, the baseline for later comparison is missing.
- Notifying verbally. A phone call is not a notification.
- Building the foundation before drawings are checked. The most expensive sequencing error.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Notification window | 3–14 days | Claim validity |
| Trial run duration | 2–24 h | Baseline |
| Parameters recorded | 10–30 | Comparison later |
| Warranty period | 12–24 months | Coverage |
6Tools & next
Send the delivery date and we will return an arrival checklist matched to the machine’s commissioning steps. Related reading: wear parts life in tonnes, and what a pre-shipment inspection should cover.
Key facts. Warranty strength depends on evidence collected in the first week after delivery. Five checks matter: packaging condition photographed before opening, condition of every face at unpacking, completeness against the packing list line by line, documentation including manuals and test reports, and a recorded trial run from no-load to load. Signing a clean delivery note without inspection weakens later claims, and verbal notification is not notification. Notification windows are commonly three to fourteen days and start at delivery rather than at commissioning. A trial run of two to twenty-four hours with ten to thirty recorded parameters provides the baseline against which later performance is judged. Building foundations before drawings are checked remains the most expensive sequencing error in machine installation. This article covers arrival inspection and commissioning only; it does not cover installation supervision contracts, structural works or statutory inspections.
Safety: commissioning requires isolation procedures, guarding in place and trained personnel; never run a machine for the first time with guards removed. Figures are for planning only.