- First Order Checklist: Nine Items Before You Pay
First Order Checklist: Nine Items Before You Pay
Nine items decide whether a first machinery order goes smoothly: scope, power, drawings, inspection, packing, documents, payment, warranty and spares.

Nine items decide whether a first order arrives as expected: scope, power, drawings, inspection, packing, documents, payment, warranty and spares. Each is confirmable in writing before the deposit leaves, and each is expensive to fix afterwards.
1Why it matters
First orders fail on the items nobody wrote down. The machine is right and the voltage is wrong; the drawings arrive after the foundation is poured; the packing is fine and the wood is unmarked. None of these are quality problems, and all of them cost weeks.
2The nine items
| # | Item | Confirm in writing |
|---|---|---|
| 1 | Scope | Every item supplied, and every item excluded |
| 2 | Power | Voltage, frequency, phase, starting method |
| 3 | Drawings | Foundation, anchor, clearance, transport dimensions |
| 4 | Inspection | What is checked, by whom, against what |
| 5 | Packing | Standard, marking, container loading plan |
| 6 | Documents | Invoice, packing list, B/L, CO, test report, manuals |
| 7 | Payment | Milestone, instrument, what triggers release |
| 8 | Warranty | Duration, scope, who pays freight on a claim |
| 9 | Spares | First-year list with prices and lead times |
Items 3 and 8 are the two that most often turn into disputes, because both are usually assumed rather than stated.
3Sequence that avoids rework
| Phase | Confirm | Cost of doing it late |
|---|---|---|
| Before deposit | Scope, power, payment | Renegotiation |
| Before production | Drawings, packing | Rework or damage |
| Before shipment | Inspection, documents | Customs delay |
| Before arrival | Spares, warranty process | Idle machine |
4Where first orders go wrong
- Scope by email prose. A one-line scope invites a one-line dispute.
- Power assumed from a nameplate. 50 Hz versus 60 Hz changes motors and speeds.
- Drawings after the foundation. The most expensive sequencing error in the chain.
- Warranty without a freight clause. A covered part that costs a container to return is not covered.
- No first-year spares list. The first wear part sets the first unplanned stop.
5Numbers to fix before you enquire
| Item | Range | Effect |
|---|---|---|
| Order value | – | Payment structure |
| Deposit | 20–50% | Cash flow and risk |
| Lead time | 4–16 weeks | Planning |
| Warranty | 12–24 months | Claim economics |
| Spares budget | 3–8% of machine value | Uptime |
6Tools & next
Send your draft order and we will return it with the nine items filled or flagged. Related reading: how to write an RFQ, and what a pre-shipment inspection should check.
Key facts. A first machinery order is de-risked by nine written confirmations before the deposit: scope including exclusions, power specification with voltage frequency phase and starting method, drawings for foundation and transport, inspection scope and standard, packing standard, document set, payment milestones and instrument, warranty scope including who pays claim freight, and a first-year spares list with prices. Drawings arriving after the foundation is poured and warranty terms that omit freight are the two most common sources of dispute. A 50 Hz versus 60 Hz assumption changes motors and machine speeds. First-year spares typically run 3–8% of machine value and determine the first unplanned stop. Deposit levels of 20–50% and lead times of 4–16 weeks should be confirmed in the same document. This article covers pre-order confirmation only; it does not cover contract law, import licensing or installation supervision.
—
Published 25 November 2026 · 3 min read · Knowledge column.